Jun
26
26
Jul
26
Aug
26
Sep
26
Oct
Contract Period
16w 2d
02-Jun
24-Sep
24-Sep
Target Period
14w 2d
02-Jun
10-Sep
10-Sep (14w 2d)
Start on Site
0d
02-Jun
02-Jun
02-Jun (0d)
Groundworks and Civils
2w 4d
02-Jun
20-Jun
20-Jun (2w 4d)
Frame
6w
09-Jun
21-Jul
21-Jul (6w)
Envelope Works
7w
23-Jun
11-Aug
23-Jun
11-Aug (7w)
SFS and Cem Board
3w
23-Jun
14-Jul
23-Jun
14-Jul (3w)
Masonry
6w 4d
26-Jun
11-Aug
26-Jun
11-Aug (6w 4d)
Cladding
3w 6d
30-Jun
27-Jul
30-Jun
27-Jul (3w 6d)
Glazing
1w 6d
07-Jul
20-Jul
07-Jul
20-Jul (1w 6d)
Internal Works
5w 1d
16-Jul
21-Aug
16-Jul
21-Aug (5w 1d)
1st Fix Partitions
1w 6d
16-Jul
29-Jul
16-Jul
29-Jul (1w 6d)
MEP Works
4w
21-Jul
18-Aug
21-Jul
18-Aug (4w)
Sprinkler Install
2w 1d
21-Jul
05-Aug
21-Jul
05-Aug (2w 1d)
1st Fix MEP
6d
24-Jul
30-Jul
24-Jul
30-Jul (6d)
2nd Fix Partitions
1w
01-Aug
08-Aug
01-Aug
08-Aug (1w)
Plastering
3w 1d
24-Jul
15-Aug
24-Jul
15-Aug (3w 1d)
2nd Fix MEP
6d
12-Aug
18-Aug
12-Aug
18-Aug (6d)
Decorations
3w 1d
30-Jul
21-Aug
30-Jul
21-Aug (3w 1d)
T&C All Areas
3w
14-Aug
04-Sep
14-Aug
04-Sep (3w)
Snagging
3w 1d
19-Aug
10-Sep
19-Aug
10-Sep (3w 1d)
Anticipated Completion
0d
10-Sep
10-Sep
10-Sep
10-Sep (0d)
Practical Completion
0d
24-Sep
24-Sep
24-Sep
24-Sep (0d)
£0k
£100k
£200k
£300k
£400k
£500k
£600k
£700k
£800k
£900k
£1m
£0k
£100k
£200k
£300k
£400k
Fire Load
10-Sep to 24-Sep (2w)
TODAY · 10-JUL
Groundworks & Civils
Complete 20-Jun
TIME
100% planned
100% actual
VALUE
£120k planned · £120k earned · ±£0
data date 10-Jul-26
Frame
4d behind
TIME
74% planned
65% actual
VALUE
£190k planned · £168k earned · −£22k
data date 10-Jul-26
Envelope
5d behind
TIME
35% planned
28% actual
VALUE
£98k planned · £76k earned · −£22k
data date 10-Jul-26
Internals
Starts 16-Jul
TIME
0% planned
0% actual
VALUE
£0 planned · £0 earned · ±£0
data date 10-Jul-26
MEP
Starts 21-Jul
TIME
0% planned
0% actual
VALUE
£0 planned · £0 earned · ±£0
data date 10-Jul-26
IP 8
/10
IV 12
/14
AFI 6
/8
C 4
/5
IP 6
/12
IV 5
/9
AFI 9
/11
C 2
/6
Frame — QA
QA tracking progress
In Progress — 8 of 10 lots
Inspected & Verified — 12 of 14 lots
Available for Inspection — 6 of 8 lots
Closed — 4 of 5 lots
data date 10-Jul-26
Envelope Works — QA
QA lagging progress
In Progress — 6 of 12 lots
Inspected & Verified — 5 of 9 lots
Available for Inspection — 9 of 11 lots
Closed — 2 of 6 lots
data date 10-Jul-26
Contract
Dates
CP
CP Only
Recovery Period
↺
Key Elements
Civils & Frame
Envelope
Internals
Internals & MEP
MEP
↺
Element Analysis
Civils
Frame
Envelope
Internals
MEP
↺
Quality
QA Status
↺
Commercial
Forecast
Actual
Sector Ave
↺
Project Risks
Peak Ops
Weather
Fire Load
↺